Construction update

The team has been continuing work on the Raigmore Active Travel Link this week while awaiting delivery information for the delayed street furniture and wood cladding. What’s been happening? Over the past week, the team has been continuing work on drainage and steps. The Travel Link’s first set of steps have been completed and preparationContinue reading “Construction update”

Construction update

Work has continued on the Raigmore Active Travel Link this week as the team awaits confirmation of delivery of the street furniture and wood cladding to finish the project. What’s been happening? Preparation of the ground for the footpath has continued over the past week, as well as the installation of kerbs. The team hasContinue reading “Construction update”

Construction update

Following last week’s update that the Raigmore Active Travel Link will face delays caused by supply issues, the team has continued working on site. What’s been happening? Work has been continuing to prepare the ground for the footpath. This is being graded, ready for the top layer of tarmac later in construction. The installation ofContinue reading “Construction update”

Delays expected to Raigmore Active Travel Link

It was confirmed this week at a Raigmore Community Council meeting that the construction of the Raigmore Active Travel Link, which was estimated to be completed 16th September, could face delays due to supply issues. Contractor Pat Munro has been faced with delays with the supply and delivery of the street furniture items which includeContinue reading “Delays expected to Raigmore Active Travel Link”

Construction update

The Pat Munro team has been busy again this week on the construction of the Raigmore Active Travel Link. What’s been happening? Work carried out this week includes drainage, plus work on handrails and guardrails. What’s happening next? This week, work to prepare the ground for footpaths will continue. The layer below the footpath isContinue reading “Construction update”

Construction update

It’s been another productive week on the construction of the Raigmore Active Travel Link, which is due to be completed in September. What’s been happening? The Pat Munro team has been carrying out drainage works this week, as well as work on handrails and guardrails. A subcontractor has also been on site to start theContinue reading “Construction update”

Construction update

Construction of the Raigmore Active Travel Link continues to progress well, as we move towards the scheduled completion date next month (September 2021). What’s been happening? Over the past couple of weeks, the team has been busy carrying out drainage works, as well as preparing handrail and guardrail foundations. Brackets have also been welded toContinue reading “Construction update”

Construction update

Work on the Raigmore Active Travel Link is progressing well and is on schedule to be completed next month (September 2021). What’s been happening on-site? This week, work will be similar to that carried out last week. The team will be continuing drainage works, as well as welding brackets to the sheet piles ready forContinue reading “Construction update”

Construction update

Construction of the Raigmore Active Travel Link continues to progress well with all work on the concrete capping beams now completed. Some temporary support structures have also been removed and taken away from the site. What’s next? This week, brackets will be welded to the sheet piles ready to hold the timber cladding that willContinue reading “Construction update”

Construction update

Construction of the Raigmore Active Travel Link continues to progress well. What’s next? Work on the concrete capping beam will start on the second line of sheet piling. This will mean that the temporary support structures on site can be removed. These temporary structures will then be taken away from the site by lorry towardsContinue reading “Construction update”