Construction update

Work has continued on the Raigmore Active Travel Link this week as the team awaits confirmation of delivery of the street furniture and wood cladding to finish the project. What’s been happening? Preparation of the ground for the footpath has continued over the past week, as well as the installation of kerbs. The team hasContinue reading “Construction update”

Construction update

It’s been another productive week on the construction of the Raigmore Active Travel Link, which is due to be completed in September. What’s been happening? The Pat Munro team has been carrying out drainage works this week, as well as work on handrails and guardrails. A subcontractor has also been on site to start theContinue reading “Construction update”

Construction update

Construction of the Raigmore Active Travel Link continues to progress well. What’s next? Work on the concrete capping beam will start on the second line of sheet piling. This will mean that the temporary support structures on site can be removed. These temporary structures will then be taken away from the site by lorry towardsContinue reading “Construction update”

Active Travel Link making good progress

The construction of Raigmore Active Travel Link remains on track for completion in September. What’s been happening on-site? There has been an increased number of deliveries over the past couple of weeks removing materials from the site. Some issues were raised over the speed of lorries entering and leaving Raigmore estate which were addressed withContinue reading “Active Travel Link making good progress”

Sheet piling at Raigmore Active Travel Link completed

Over the past two weeks, the installation of sheet piling has been taking place on-site. This was the most disruptive phase of the works so we would like to thank Raigmore residents and those affected for their patience. What’s next? Now that sheet piling has been installed, the next step is phase two of earthworks,Continue reading “Sheet piling at Raigmore Active Travel Link completed”

Sheet piling progress update

Last week saw the start of the sheet piling phase of construction for the Raigmore Active Travel Link. This phase is the most disruptive phase of the works and has caused some noise and vibrations for which we apologise. This phase is expected to be completed by 18th June. Throughout this period and until workContinue reading “Sheet piling progress update”

Footpath and lane closures

To allow work on the Raigmore Active Travel Link to be carried out, some footpath and lane closures will be in place. Footpath closure The footpath leading from the Raigmore Interchange to Raigmore Estate at the end of MacKintosh Road will be closed from 4th May for the duration of the works, which are dueContinue reading “Footpath and lane closures”

Raigmore Active Travel Link works to begin

Preparation work to establish an active travel link in the Raigmore area of Inverness is set to begin on 19th April 2021. As part of the Inverness City Active Travel Network (ICATN), the Raigmore Active Travel Link will consist of a link to encourage walking, wheeling and cycling from the Raigmore Estate and existing GoldenContinue reading “Raigmore Active Travel Link works to begin”