Latest updates

Construction update

Work continues on the construction of the Raigmore Active Travel Link, as the Pat Munro team works towards a completion date of late November. What’s been happening? Last week, the team erected edge rail fencing, laid soil, continued work on the remaining two sets of steps and installed street lighting columns. The team has alsoContinue reading “Construction update”

Construction update

Construction of the Raigmore Active Travel Link continues, with the team preparing the site before the delivery of street furniture and wood cladding for the sheet piles. A date has also been confirmed for the felling of dead and diseased trees. What’s been happening? Over the past week, the team has continued work on theContinue reading “Construction update”

Construction update

The Pat Munro team provided an update on construction at this month’s Raigmore Community Council meeting. Taking place on Zoom on Monday 27th September, a new timeline for the completion of works was also given. Work completed Work completed since the last Raigmore Community Council meeting includes timber cladding rails on sheet piles, verging works,Continue reading “Construction update”

Construction update

The team has been continuing work on the Raigmore Active Travel Link this week while awaiting delivery information for the delayed street furniture and wood cladding. What’s been happening? Over the past week, the team has been continuing work on drainage and steps. The Travel Link’s first set of steps have been completed and preparationContinue reading “Construction update”

Construction update

Work has continued on the Raigmore Active Travel Link this week as the team awaits confirmation of delivery of the street furniture and wood cladding to finish the project. What’s been happening? Preparation of the ground for the footpath has continued over the past week, as well as the installation of kerbs. The team hasContinue reading “Construction update”

Construction update

Following last week’s update that the Raigmore Active Travel Link will face delays caused by supply issues, the team has continued working on site. What’s been happening? Work has been continuing to prepare the ground for the footpath. This is being graded, ready for the top layer of tarmac later in construction. The installation ofContinue reading “Construction update”

Construction update

The Pat Munro team has been busy again this week on the construction of the Raigmore Active Travel Link. What’s been happening? Work carried out this week includes drainage, plus work on handrails and guardrails. What’s happening next? This week, work to prepare the ground for footpaths will continue. The layer below the footpath isContinue reading “Construction update”

Construction update

It’s been another productive week on the construction of the Raigmore Active Travel Link, which is due to be completed in September. What’s been happening? The Pat Munro team has been carrying out drainage works this week, as well as work on handrails and guardrails. A subcontractor has also been on site to start theContinue reading “Construction update”

Construction update

Construction of the Raigmore Active Travel Link continues to progress well, as we move towards the scheduled completion date next month (September 2021). What’s been happening? Over the past couple of weeks, the team has been busy carrying out drainage works, as well as preparing handrail and guardrail foundations. Brackets have also been welded toContinue reading “Construction update”

Loading…

Something went wrong. Please refresh the page and/or try again.


Sign up to receive updates

Receive email updates on the construction programme