Raigmore Active Travel Link officially opened

The Raigmore Active Travel Link was officially opened on 8th March 2022 by elected Council Members, Raigmore Community Council, and Primary 5 pupils from Raigmore Primary School nearby. The pupils are Junior Road Safety Officers and play an important part in the primary school, helping to raise road safety awareness and promote road safety issuesContinue reading “Raigmore Active Travel Link officially opened”

Raigmore Active Travel Link is open!

We are delighted to confirm that the Raigmore Active Travel Link is now open. The Raigmore Active Travel Link aims to encourage walking, wheeling and cycling from the existing Golden Bridge to the Raigmore Interchange. The route allows access from the Raigmore Interchange to Inverness Campus and onwards to Inverness Shopping Park, removing the needContinue reading “Raigmore Active Travel Link is open!”

Construction update

The Raigmore Active Travel Link is now in the final phase of construction, with the delivery of outstanding materials coming next week. It is hoped that the Active Travel Link will open to the public shortly after this. We apologise, once again, for the delays and any inconvenience these may have caused. Unfortunately, these haveContinue reading “Construction update”

Construction update

It is hoped that the Raigmore Active Travel Link will be completed and open to the public within the next few weeks, following delays caused by supply issues. We apologise for any inconvenience caused by these delays. What’s been happening? Handrail and guardrail installation has continued, as has landscaping work. Work has also continued onContinue reading “Construction update”

Construction update

The Raigmore Active Travel Link is nearing completion, following delays caused by supply chain issues. It is hoped that the Travel Link will be completed and open to the public at the end of this month (January 2022). We apologise for any inconvenience caused and thank you for your continued patience. What’s been happening? SinceContinue reading “Construction update”

Construction update

Work on the Raigmore Active Travel Link will continue until the Christmas break on Wednesday 22nd December. It was hoped that work would be completed by Christmas, however, there is some outstanding work to be completed due to delays caused by supply issues. We apologise for any inconvenience caused and thank you all for yourContinue reading “Construction update”

Construction update

The majority of work on the Raigmore Active Travel Link has now been completed. There is still some outstanding work to be completed on handrails and guardrails, due to delays caused by supply issues. It is hoped that all work will be completed by Christmas. What’s been happening? Office and welfare cabins have now beenContinue reading “Construction update”

Construction update

We are now entering the final few weeks of construction of the Raigmore Active Travel Link. The majority of work has now been completed, however there will be some outstanding work to complete on handrails and guardrails, due to delays caused by supply issues. It is hoped that all work will be completed by Christmas.Continue reading “Construction update”

Construction update

The Raigmore Active Travel Link is nearing completion, with the majority of work due to be finished over the next couple of weeks. After this, the only outstanding work will be the final parts of guardrail and handrail installation, which is hoped to be completed by Christmas. These delays have been caused by supply chainContinue reading “Construction update”

Construction update

The Raigmore Active Travel Link is nearing completion, however, there have been some further delays in the delivery of materials for the guardrail and handrail construction. The majority of works will now be completed in early December with only the guardrail and handrail to be completed on the run-up to Christmas. It is hoped thatContinue reading “Construction update”