Construction update

It is hoped that the Raigmore Active Travel Link will be completed and open to the public within the next few weeks, following delays caused by supply issues.

We apologise for any inconvenience caused by these delays.

What’s been happening?

Handrail and guardrail installation has continued, as has landscaping work. Work has also continued on the final section of fencing surrounding the site.

What’s happening next?

Work on the installation of the final sections of handrail and guardrail, as well as the final section of fencing, will continue. Street lighting will also be connected this week.

Landscaping work will be ongoing over the next few weeks, until after the Travel Link has opened.

The entrance to the site will be tidied and returned to its previous condition when work is completed.

Get in touch

If you have any questions or concerns, please get in touch with the team on site or via email or phone on raigmoreatl@whalelikefish.co.uk or 01463 830 390.