Construction update

The team from Pat Munro has been continuing work on the Raigmore Active Travel Link, with completion due late this month (November 2021).

What’s been happening?

Kerbing works has continued in preparation for the installation of the street furniture and the remaining cladding. Landscaping work has also continued with topsoil being laid around the verges.

What’s happening next?

This week, the final section of drainage, as well as the kerbing, will be completed. The first layer of surfacing will be completed, and handrails and guardrails will be installed. Existing fencing will be cleared, and new timber fencing will be installed. Street lighting will also be completed ahead of commissioning next week.

Delivery of the final wooden cladding is expected over the next couple of weeks to enable the sheet pile cladding to be completed.