Construction update

Construction of the Raigmore Active Travel Link continues to progress well. The next week will see work similar to the previous being carried out.

What’s been done?

Construction of the concrete capping beam at the top of the sheet pile wall has been in progress over the past week. Lorries have been arriving at the site through Raigmore estate to deliver the concrete needed for this.

What’s next?

Work on the concrete capping beam will continue, with some lorries arriving to deliver materials. It is anticipated that concrete deliveries will take place over a few days this week.

Lorry drivers have been reminded of the 20mph speed limit throughout the estate but if you have any concerns relating to this, or anything else, please get in touch using the contact information below.

The team will also be starting drainage works and preparing the foundations for handrails.

Any questions or concerns?

As always, please get in touch if you have any questions or concerns.

If you would like to speak with someone on-site, please wait at the site entrance where a member of the team will meet you. Or you can contact the team via email or phone on raigmoreatl@whalelikefish.co.uk or 01463 830 390.